ENGR 103 - Spring 2016
Freshman Engineering Design Lab
Freshman Engineering Design Lab
“Emergency
Soil Stabilizing Method”
Final Report
Date Submitted: May 30, 2016
|
|
Submitted to:
|
Grace Hsuan, ghsuan@coe.drexel.edu
|
Group Members:
|
Jennifer Cromley, jlc524@drexel.edu
|
|
Chris Laudando, cvl27@drexel.edu
|
|
Jessica Butterly, jab592@drexel.edu
|
|
Matthew VanTrieste, mjv54@drexel.edu
|
|
Keith Colon, krc84@drexel.edu
|
Abstract:
The Emergency Soil Stabilizing
Method was created to prevent degradation of soil slopes that occurs too
quickly for a long term solution to be immediately applied. The goal of this
project was to design a method that would stabilize a degrading slope in a
three step process until conditions are suitable to implement a long term
solution. The first step of the process
is to construct a brick toe wall, which will quickly give more support to the
slope. The second step, an intra-soil grid, is a unique structure that
stabilizes the slope internally. It is biodegradable and inserted directly into
the soil. The last step is to apply a surface blanket to prevent erosion.
Surface blankets are commonly seen and may contain seeds to grow vegetation as
a long term solution. There were two majors tasks completed - rain simulations
and applied pressure tests. These tests were conducted on a constructed slope
inside a plastic container. Technical challenges faced were the inability to
test due to weather, (most tests needed to be conducted outside), and
simulating the rain at a constant rate. The final deliverable of the Emergency
Stabilizing Method are the toe wall and intra-soil grid within the test area,
and the assertion of the optimal method of stabilization.
1
Introduction
1.1
Problem Overview
The idea of an emergency soil stabilizing method was
motivated by the difficulties found in preventing and coping with slope
degradation. The unstable nature of a degrading slope can create problematic
situations for implementing a long term solution. The goal of the Emergency
Soil Stabilizing Method was to find a way to quickly stabilize a slope without
damaging the surrounding environment. The process is not intended to stand
alone as a long term solution, but rather provide time for a long term solution
to be put in place. The model of the Emergency Soil Stabilizing Method
completed was a relatively low cost project. However, if it were to be
implemented in full-scale the cost would be much greater. The nature of the
project, being a miniaturized version, also leads to many constraints. The most
prominent issue is that not all factors of true soil erosion can be included.
Soil on a slope can degrade due to high winds, heavy rainfall, sustained
pressure, human interaction, and a variety of other factors as well. The
isolated factors that were focused on
for the Emergency Soil Stabilizing Method included rainfall and applied
pressure.
1.2
Existing Solutions
1.2.1
Planting
Vegetation
A long term solution to soil erosion that currently exists
is the planting of vegetation along the degrading slope. The root system that
the vegetation develops provides a natural structure that stabilizes the slope.
Results from an experimental study show that plant root systems were vital for
the conservation of soil and water on a slope experiencing soil erosion
[5]. The Emergency Soil Stabilizing
Method would be carried out if planting vegetation is not possible due to
seasonal issues or if the slope would be beyond repair before the roots of vegetation
could take place.
1.2.2 Toe Wall
Toe walls are not a new invention and have been in use for
many years to stop hills from collapsing onto man-made structures. These
structures are generally made from large stones stacked on each other to the
appropriate height. Concrete and other materials may also be used as structural
demands are changed on a situational basis. Toe walls are generally long term
solutions and are, for the most part, successful. The main reason why a toe
wall would fail is because of improper drainage behind the wall. Water builds
up behind the wall in the soil, and the excess weight added by the water causes
a mechanical failure in the wall. The most heavily affected section will
subsequently fail.
1.2.3 Erosion Control Blanket
Erosion control blankets are already a widely used and
effective method to halt the process of erosion. Examples of items specifically
designated for erosion control exist in such diversity that one can be
implemented on almost any slope, no matter the angle or contour [1]. Many are
also designed with long term solutions in mind, and as such are specifically
designed to protect seeds that will prevent erosion long after the seed blanket
has degraded.
1.3
Project
Objectives
1.3.1 Toe Wall
One objective of this project is to create a wall that can
stand for as long as it takes to install a long term solution, such as plants.
A key factor in the design is creating something that can be implemented
quickly while keeping strength. There must be proper drainage throughout the
toe wall for it to be effective. Several efficient models of toe walls have been
create and tested prior to the development of this project.
1.3.2 Intra-soil Grid
While toe walls and surface covers are already typically
employed solutions, the intra-soil grid is a more unique concept to this
project. This concept was born from the limitations associated with the wall
and cover. Toe walls can act as dams and surface coverings can prevent
superficial erosion, but neither cannot prevent soil shifting and partial slope
collapse. The intra-soil grid is meant to help stabilize the slope directly.
The grid itself would be laid into the slope and would penetrate down to a
reasonable depth. The depth varies depending on the model. Design goals for
this aspect of the project include using biodegradable materials, creating a
method of easy application, providing reasonable support with minimal use of
resources, and creating a system that can accommodate for irregular surface
areas. Different models were produced, such as a simple model shaped either
like an egg crate, noted as Phase 1, or small plugs, noted as Phase 2, which
can be seen below in Figures 1A and 1B.
Figure 1A: Grid Phase 1. Figure 1B: Grid Phase 2.
From these simple designs a more complex model was
developed, which was designed to not only provide support, but also catch
eroding soil. The model used for tests included hot glue for stability, but
this material would not be used in a final product. This unit acts more as a stake,
and may be more tedious to install then other models, but potentially provides
greater aide. This can be seen in Figure 2
Figure 2: Grid Phase 3.
1.3.3 Surface Cover
Surface coverings are already manufactured and widely used.
Because of this, it was determined that the most effective and efficient way to
implement a surface covering was to use one that already exists. A combination
of modern seeding techniques and an existing type of biodegradable erosion
control blankets, which can be implemented as the seeds are planted, will
provide the desired effect while eliminating the need for any extraneous
research and manufacturing.
2
Technical
Activities
2.1
Rain Simulation
One of the main factors being tested in this project was
soil erosion due to rainfall. There were many designs
initially considered to simulate rain. The design for rain simulation
continuously changed throughout testing. The first method tested used window
screening. The item purchased could be pulled for extension but for the
purposes of the project was left as a double screen. The screen can be seen in
Figure 3.
Figure 3: Screen used for rain simulation.
Various materials were put between the two layers of
screening for testing. The first test was carried out with cheese cloth and the
second with weed block. The cheese cloth absorbed the water instead of allowing
it to pass through, but the weed block seemed to distribute the water more
evenly. It was porous enough to allow the passage of water, but not so thin
that the water would pass through as a single stream.
However, testing at later time showed faults in the method
of rain simulation with weed block between the layers of screen. If too much
water was poured at once, it would pool on the surface of the screen rather
than pass through. The next method consisted of just the screen at
approximately 32-in from the bottom of the control environment, with the water
being poured approximately 16-in from the top of the screen. This method was
tested on the soil slope. The only change that was visible to the human eye was
a more rounded slope edge as opposed to the angled slope initially built.
However calculations proved that the slope angle deteriorated by approximately
two degrees.
This method was later refined from the pouring of water
directly onto the screen to pouring the water into a cup with a small hole in
the bottom. This cup allowed for a more constant rate of rainfall if the water
inside was kept at the same volume. The goal for the simulation was to not
exceed an approximate rain fall of two inches per hour, as this is deemed a
“violent” storm. The cup method was
tested by carrying out a simulation for nine minutes and ten seconds. A small
graduated cylinder was placed in the bottom of the control environment to
measure the volume. The amount of rainfall after this time period was 1.5-in,
which led to an hourly projection of 9.8-in per hour. The size of the cup and
the hole were then reduced.
This rain simulation method was then used as a baseline test
for the three phases of grid structures. The measurements and calculations for
this testing can be viewed in the Appendix.
2.2
Applied Pressure
Various applied pressure tests were done on the slope of the
soil. There was initially one large 12-lb brick placed on the smooth top of the
slope. The brick was then cut into two for a better fit on the slope. In these
simulations it was desired that the slope would fail. The failure of the slope
would be the baseline that the Emergency Soil Stabilizing method could be
compared to. Figure 4 shows the set up of the applied pressure test.
Figure 4: Applied pressure testing.
This pressure testing was done on the control slope and the
three phases of grid structures. The slope did not fail under any of these
tests. However, changes did occur. The measurements and calculations for these
tests can be viewed in the Appendix.
2.3
Project Timeline
Throughout
the progression of the project, the Emergency Stabilizing Method has followed
the initial schedule made in the project proposal with only minor changes. The
project had a few delays due to testing and insufficient data. One major factor
that caused the control testing to be longer than planned was simulating rain,
as all of the original ideas did not achieve the desired results. Once the
simulation was effective, the project continued with ease. Another issue was
the weather because testing can not be performed effectively inside without
creating a mess. The general project timeline can be seen in Table 1.
Table 1: Project
Timeline
|
|
|||||||||
Task
|
1
|
2
|
3
|
4
|
5
|
6
|
7
|
8
|
9
|
10
|
Initial Planning
|
x
|
x
|
|
|
|
|
|
|
|
|
Getting the Materials
|
|
x
|
x
|
|
|
|
|
|
|
|
Control Testing
|
|
|
x
|
x
|
x
|
|
|
|
|
|
Toe Wall
|
|
|
|
|
|
x
|
x
|
|
|
|
Rain Simulation Design and Testing
|
|
|
|
x
|
x
|
x
|
x
|
x
|
x
|
|
Grid Structure
|
|
|
|
|
|
x
|
x
|
x
|
x
|
|
Testing in Combination
|
|
|
|
|
|
|
|
x
|
x
|
|
Final Report Drafting
|
|
|
|
|
|
x
|
x
|
x
|
x
|
x
|
2.4
Project Budget
The budget was relatively low due to the amount of research
and testing being conducted compared to the complete fabrication of a product.
Expenses stemmed from four main components: the control environment, toe wall,
intra-soil grid, and the seed blanket for the surface. Various materials such
as the soil used, small garden shovels, Styrofoam cups, etc. were obtained
through resources already available and therefore had no impact on the budget.
The total cost to carry out the Emergency Soil Stabilizing Method was $124.11.
Table 2 outlines the products purchased, their cost, and a brief description of
their use.
Table 2: Project Budget
Item
|
Quantity
|
Cost
|
Brief
Description of Use
|
Home Depot Bucket
|
2
|
$5.97
|
Collect water used in testing and carry materials
|
Rumblestone
|
2
|
$3.76
|
Weight for the top of the slope
|
Gloves
|
1
|
$3.98
|
Creating soil slope without getting dirty
|
Paint Rags
|
1
|
$3.97
|
Intial idea to simulate rain
|
Weedblock
|
1
|
$5.00
|
Line the bin to add more friction and makes the
water go through the slope
|
24” Window Screen
|
1
|
$7.68
|
Water is poured through to simulate rain
|
Jiffy Strips Pots
(grid)
|
2
|
$5.56
|
Material for grid structure
|
Jiffy Strips Pots (round)
|
2
|
$4.56
|
Material for grid structure
|
Bounty Paper Towels
|
1
|
$1.00
|
Clean up the water
|
Plastic Latch Box
|
2
|
$15.94
|
Hold the slope and testing is conducting inside of
it
|
Brick (thin)
|
3
|
$1.95
|
Toe wall
|
Paver Saw Rental
|
1
|
$64.74
|
Cut bricks into specific shapes for construction of
toe wall
|
Total Cost
|
|
$124.11
|
|
3
Results
The initial goal of this project was to test a toe wall,
surface blanket, and intra-soil grid together under the condition of heavy rain
and pressure. Due to limitations on time, the testing with the surface cover
and toe wall was not achieved. The decision to cut these from testing, but not
the methodology, was validated by the significant amount of outside testing and
data that predates the start of this project. Both toe walls and surface
blankets are standard methods used in the field for stabilization. Furthermore,
as research continued it was found that an optimal toe wall design was not
achievable with the resources and materials acquired.
The goals of the project were restructured, and the main
product to be tested became different samples of the intra-soil grid. Three
versions of the grid design were tested. The three structures were tested under
pressure and rain conditions to see how the change in slope angle differed
between grid design and the control test. The grids were also tested to see
what change there was in the slope during their application process. The angle
was chosen as the test variable due to its ability to capture the relationship
between the length, height and slope of the soil structure. It would have been
ideal to have at least three test trials for each scenario, but as the project
evolved and different test methods were implemented only 1 trial of each test
was possible.
In the control test for pressure the angle change was 4.3%.
Grid 1 and 3 had changes around 6 %, which were deemed too small of differences
and making viability in terms of pressure inconclusive for these models. For
Grid 2 there was an 18% change, thus grid 2 weakened to the slope to
degradation from pressure.
For the rain simulation the control test yielded on 8.74%
change. The data was again inconclusive in terms of Grid 1, but showed some
promise for Grid 2, which had 4.5% change. The best results were yield from
Grid 3 in which there was only 3.01% change in the angle.
The final set of data showed that the slope angle was
changed by 8.4% by Grid 1, 19.8% by Grid 2 and 3.75% by Grid 3. The overall
analysis of the data indicates that Grid 2 is overall damaging to the slope
structure, and Grid 3 has the most promise out of all the models. Though Grid 3
yield the best results, the design would need refinement and more thorough
testing before implementation.
4
Discussion
Part of the focus of this project was that the design could
be implemented at full-scale. For obvious reasons the materials used in small
scale tests could not be used on a full-scale system, so research was done to
determine what materials could be used. It was found that bamboo is the only
biodegradable material strong enough to make the intra-soil grid. Bamboo
plates, which would be similar to the walls of the grid, are already
manufactured [2]. Biodegradable stakes, some of which are as strong as or
stronger than metal stakes of the same size, can be used to hold the grid in
place [3]. As previously stated, existing erosion control blankets and seeding
methods would be used for the seed blanket. Erosion control blankets already
come in amounts large enough to be used in a full-scale implementation.
Given more time, this project could have been improved
through more extensive testing. Different materials for the toe wall and
intra-soil grid could have been tested at the small scale to allow further
analysis on how this project could be scaled up in size. These results could
also be paired with the cost of these materials to maximize the cost effectiveness
of the final product. Different designs of the wall and bridge could also have
been planned and tested to ensure that the design’s effectiveness is maximized.
There were few possible errors in this project. Errors in
calculation, measurement, and estimation are the most likely to have occurred.
Any experimental errors would have been obvious in the results of the
experiment, and as such they would have been corrected at the time.
Various concepts and practical skills were learned through
the process of developing this project. The theoretical concepts surrounding
the effectiveness of retaining walls, as well as their application, were
demonstrated. Concepts involving rain rate and its erosive effect on the
dimensions of a slope were also an integral part of experimentation.
5 References
[1] “A.M.
Leonard Tools for the Horticultural Industry since 1885.,” Straw-Coconut
Erosion Control Standard Blanket, 8ft x 113ft Roll. [Online]. Available at:
http://www.amleo.com/straw-coconut-erosion-control-standard-blanket-8ft-x-113ft-roll/p/sc3000/.
[Accessed: 09-May-2016].
[2]
“Bambu 063200 9’ Disposable Square Bamboo Plate - 25 / Pack,” WebstaurantStore.
[Online]. Available at:
http://www.webstaurantstore.com/bambu-063200-9-disposable-square-bamboo-plate-25-pack/999063200.html.
[Accessed: 09-May-2016].
[3]
“Biodegradable Ground Stakes – 500 per Box,” ARBICO Organics. [Online].
Available at:
http://www.arbico-organics.com/product/biodegradable-ground-stakes/garden-tools-supplies.
[Accessed: 09-May-2016].
[4]
“Walls come tumbling down,” Colorado Springs Independent. [Online]. Available
at:
http://www.csindy.com/coloradosprings/springs-retaining-walls-fail-without-maintenance-inspections-and-permits/content?oid=3133800].
[Accessed: 09-May-2016].
[5] X.
Zhang, G. Q. Yu, Z. B. Li, and P. Li, “Experimental Study on Slope Runoff, Erosion
and Sediment under Different Vegetation Types,” Water Resour Manage Water
Resources Management, vol. 28, no. 9, pp. 2415–2433, 2014 [Accessed:
09-May-2016].
6 Appendix
Table Set 1.1: Pressure Control Test
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
Pre-Pressure
|
15.3
|
23.5
|
28.93
|
33.56
|
Immediately
Post Pressure
|
10.7
|
14.15
|
18.13
|
37.32
|
30 mins Post
Pressure
|
10.6
|
14.65
|
17.83
|
35.71
|
Change
|
|
|
|
4.31%
|
Table Set 1.2: Pressure with Grid 1
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
Pre-Pressure
|
10.5
|
19.55
|
24.3
|
29.11
|
Immediately
Post Pressure
|
10.67
|
18.8
|
23.3
|
30.92
|
30 mins Post
Pressure
|
10.5
|
20
|
23.9
|
28.98
|
Change
|
|
|
|
6.27%
|
Table Set 1.3: Pressure with Grid 2
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
|
Pre-Pressure
|
12.25
|
18.5
|
21.67
|
32.33
|
|
Immediately
Post Pressure
|
12.15
|
18.45
|
21.2
|
32.59
|
|
30 mins Post
Pressure
|
10.85
|
19.75
|
21.17
|
26.72
|
|
Change
|
|
|
|
18%
|
Table Set 2.1: Rain Simulation
Control
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
Pre-Rain
|
14.25
|
23
|
27.8
|
32.26
|
Post-Rain
|
13.6
|
24.3
|
28.1
|
29.44
|
Change
|
|
|
|
8.74%
|
Table Set 2.2: Rain Simulation with
Grid 1
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
Pre-Rain
|
13.9
|
25.1
|
28.2
|
27.63
|
Post-Rain
|
13.3
|
25.4
|
26.8
|
25.33
|
Change
|
|
|
|
8.3%
|
Table Set 2.3: Rain Simulation with Grid 2
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
Pre-Rain
|
12.25
|
22.15
|
29.25
|
31.49
|
Post-Rain
|
12.25
|
23.85
|
31
|
30.06
|
Change
|
|
|
|
4.5%
|
Table Set: 2.4: Rain Simulation with Grid 3
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
Pre-Rain
|
11.25
|
18.8
|
29.65
|
34.6
|
Post-Rain
|
11
|
19.55
|
29.4
|
33.22
|
Change
|
|
|
|
3.01%
|
Table Set 3.1: Grid 1 Application
Movement
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
Pre-Grid
|
11.15
|
21.75
|
28
|
27.878
|
Post-Grid
|
11.35
|
21.95
|
29.13
|
30.44
|
Change
|
|
|
|
8.4%
|
Table Set 3.2: Grid 2 Application
Movement
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
Pre-Grid
|
12.2
|
22.1
|
27.2
|
25.49
|
Post-Grid
|
12.06
|
22.2
|
28.03
|
30.544
|
Change
|
|
|
|
19.8%
|
Table Set 3.3: Grid 3 Application
Movement
|
Ave. Height
(cm)
|
Ave. Length
(cm)
|
Ave. Slope
(cm)
|
Angle ⁰
|
Pre-Grid
|
11.25
|
23.2
|
29.95
|
29.05
|
Post-Grid
|
12.05
|
23.6
|
31.05
|
30.14
|
Change
|
|
|
|
3.75%
|
No comments:
Post a Comment