Tuesday, May 24, 2016
Week 9 Lab Goals
The goals for the lab today is test using the water and the grid, and to start making the presentation for next week and have that finished by the end of the week due to majority of the group heading home for the weekend.
Intrasoil Grid Phase 2
As the initial design for the grid was being created, the leftover material proved useful for a second kind of grid. This grid is disconnected and instead of supplying an outline of a structure, the pieces enclose the soil. A picture can be seen below:
The same measurements were taken as in phase 1. The angle decreased only by .8% upon applying immediate pressure. After 30 minutes, the angle decreased by another 18%. So far, the grid structures may actually be weakening the slope instead of helping. There are a few more that need to be tested. Grid structures 1 & 2 also need to be tested under rain simulation.
The same measurements were taken as in phase 1. The angle decreased only by .8% upon applying immediate pressure. After 30 minutes, the angle decreased by another 18%. So far, the grid structures may actually be weakening the slope instead of helping. There are a few more that need to be tested. Grid structures 1 & 2 also need to be tested under rain simulation.
Intrasoil Grid Phase 1
This weekend, a few of the grid designs were tested under applied pressure. The first tested was our very initial design, simply structural squares. A photo can be seen below:
The first test resulted in failure after less than a minute due to the container being bumped. The next test was successful and ran for 30 minutes with the bricks used as applied pressure. Measurements were taken before applying pressure, immediately after, and after the 30 minute time interval. The angle from the first stage to second had a 6.22% increase. This may be due to the compression of the soil as the bricks were laid or from sliding of the soil. The change between immediately after and after 30 minutes was a 6.27% decrease.
A decrease shows that the soil eroded. This may have to take into the account the change in slope as a result of putting the grid in place. Testing on these changes have been done and will be added to the blog in coming posts. This angle decrease is a larger percent from that of the toe wall. Multiple structures of the grid will be tested in the coming week.
Wednesday, May 18, 2016
First Toe Wall Test
Tonight the first testing of a toe wall was done. Below is a picture of the set up once the bricks were removed from the soil.
Measurements were taken before the bricks were placed, immediately after the bricks were placed, and 30 minutes after the bricks were placed. Before pressure was applied, the angle was approximately 32.26 degrees. As the pressure was applied there was visual degradation. Some of the soil compressed while a lot of it slid down the slope. The angle changed 11.45% between these two stages. After 30 minutes the new angle was 27.93 degrees. This was only a 2.21% decrease from immediately after the bricks were placed. While there was still soil degradation, this test of the toe wall showed less change than the pressure applied without a barrier.
It is important to note that at approximately seven minutes in one of the bricks being used for applied pressure fell from the slope. It was replaced so that the simulation could continue. This may have also been a cause of error in this test. However, it can be viewed as success because it may have fallen from a gradual loss of soil from beneath it. We want an unstable slope to begin with so we can test our methods to see if they prevent/slow degradation.
Tuesday, May 17, 2016
Results from New Pressure Test Design
The results from the new pressure test design were consistent with degradation of soil, as the slope angle decreased by 3.83%. The measurements from the height, slope, and bottom did not change as expected. The slope actually decreased instead of increasing, the bottom increased very slightly, and the height remained almost exactly the same. We think the change in angle came from a compression of the soil rather than the soil sliding but both are issues within soil erosion. The measurements were taken from immediately after bricks were placed and after 30 minutes of them being on top of the soil.
This new style of testing can have improvements in the future, such as where to place the bricks. If we decide to continue using the new design of slope, it will be carried on through toe wall and rain simulation testing.
This new style of testing can have improvements in the future, such as where to place the bricks. If we decide to continue using the new design of slope, it will be carried on through toe wall and rain simulation testing.
New Pressure Test Design
In previous trials a small ledge was made at the top of the slope to create a place to place bricks, like so:
This structure is actually very stable and shows little changes, so the group decided to try another form of test test slope:
This structure is actually very stable and shows little changes, so the group decided to try another form of test test slope:
Not only is there more immediate change, bu the measurements are slightly easier, though there are more. The bricks are placed on the slop and allowed to shift the soil downward. measurements are taken before the placement, immediately after the placement and 30 mins after placement. This test is still in the trial stage, so moving forward it may or may not be the standard.
Current Research
The strength of the wall varies depending on factors such as the materials used, the design of the wall and the type of soil behind the wall. However, one factor remains constant between all walls, water pressure behind the wall. This factor can make or break most walls. The toe wall's defense is proper irrigation.Without this system, the wall is bound to have a short lifespan.
"Built right, he says, a retaining wall can outlast most people. But like any structure, their lifespan depends on how they're built. A wall built of railroad ties isn't likely to last as long as one made of concrete blocks, but even a concrete block wall can fail early. A lot of factors play into lifespan including: the soil type behind the wall, drainage around the wall, the material the wall is made of, and how strong the wall's foundation is.
"There's a lot of different ways to design [walls]," he says. "Ensuring that there's low water and water pressure behind [the wall] is critical.""
Walls Come Tumbling Down, J. Adrian Stanley, (Article found Here)
"Built right, he says, a retaining wall can outlast most people. But like any structure, their lifespan depends on how they're built. A wall built of railroad ties isn't likely to last as long as one made of concrete blocks, but even a concrete block wall can fail early. A lot of factors play into lifespan including: the soil type behind the wall, drainage around the wall, the material the wall is made of, and how strong the wall's foundation is.
"There's a lot of different ways to design [walls]," he says. "Ensuring that there's low water and water pressure behind [the wall] is critical.""
Walls Come Tumbling Down, J. Adrian Stanley, (Article found Here)
Rain Control Test
Last week, 3 tests were preformed, 2 pressure and 1 rain test. Unfortunately measurement errors made during the pressure tests that made the data unusable. The rain test data, however, was viable. The test preformed without pressure or an upper shelf on the slope. The rate of rain was 1.5 inches per hour and the slope was subjected to the rain simulation for 30 minutes. Measurements showed that that the angle of the left slope decreased by 8.8% and the right side angle of the slope by 9.4%. Qualitative investigation showed that there was erosion, but on very small, and near impossible to measure scale. This team has the ability to perform a test that will simulate approximately 6.5 inch/hour rain. this simulation may be subjected to the slope.
Week 8 Lab
The goal for the lab today is to test the toe wall and grid system under pressure to see if there is a difference from the control data.
Thursday, May 12, 2016
First Successful Applied Load Test
This week in lab we were able to get results from our applied load testing. After 30 minutes, there was no visible change but the calculations prove shifting took place. Initially, the angle was calculated to be 35.8 degrees. The calculated angle after applying the bricks was 32.5 degrees. A decrease in angle is consistent with soil degradation because the slope becomes gradually flatter.
Tuesday, May 10, 2016
Week 7 Lab
For today's lab, we are testing the rain simulator again to get a slower rate and to make a slope that will collapse under the pressure of the weight
Saturday, May 7, 2016
Applied Load Test 2
During Week 6 lab we performed another applied load test. This time, the soil was dry and a new slope was built. The measurements for the initial slope are shown in the picture:
After 30 minutes of applied pressure, the calculations gave an angle greater than the initial angle.
This is inconsistent with predicted soil erosion. There could have been errors in measurements that caused this inconsistency. For improvements, we can make the initial slope steeper. We will continue to test. Our hope is to find a slope that will fail so that we can implement our solutions to stabilize it.
After 30 minutes of applied pressure, the calculations gave an angle greater than the initial angle.
This is inconsistent with predicted soil erosion. There could have been errors in measurements that caused this inconsistency. For improvements, we can make the initial slope steeper. We will continue to test. Our hope is to find a slope that will fail so that we can implement our solutions to stabilize it.
Tuesday, May 3, 2016
Week 6 Lab goals
The main goal of the lab today is to get the rain rate down and getting the consistency of it. We are also testing the slope under pressure to see how it reacts under pressure
Monday, May 2, 2016
Group Meeting on May 2nd
Meeting goals for tonight are to figure out why some images are not showing up on the site, finish the blog for the blog check, final report drafting and when and where to test next.
Sunday, May 1, 2016
Drying the Soil
As mentioned previously, the testing needs to be done while the soil is drier. It does not need to be entirely dried out, as in nature it is possible for a rainstorm to occur before the soil has dried from previous precipitation, but the soil should be around the natural state in which we obtained it. (The soil from southern New Jersey should be very dry, while the soil from Pennsylvania woods is naturally dense). Due to our time constraints we decided to speed the process by using a hair dryer to take moisture out of the soil. With this in mind our next rain simulation will only be done when absolutely necessary.
Blow Drying the Soil:
We took 2-3 "garden-shovel-fulls" at a time in a separate plastic container. We placed the lid over half of the box and used flexible cardboard to keep soil from escaping out the back and the remainder of the top of the box.
Here are some before and after pictures of the soil.
Blow Drying the Soil:
We took 2-3 "garden-shovel-fulls" at a time in a separate plastic container. We placed the lid over half of the box and used flexible cardboard to keep soil from escaping out the back and the remainder of the top of the box.
Here are some before and after pictures of the soil.
Applied Load Test
This weekend the team decided to conduct a test with only a load applied to the slope (no other factors tested). The slope was built at approximately a 45 degree angle, steeper than built before. At this point in the project, we want the slope to fail so that we can test our solutions to fix that same kind of slope. We placed two bricks on the top of the slope which created a load of approximately 98 N. After watching for 30 minutes, there was no change or collapse in the slope.
The problem with this test was that the soil was still wet from our previous rain simulation. The moisture in the soil caused it to be very closely packed which would prevent it from failure under our tests. The next applied load test will be conducted when the soil is dried out.
The problem with this test was that the soil was still wet from our previous rain simulation. The moisture in the soil caused it to be very closely packed which would prevent it from failure under our tests. The next applied load test will be conducted when the soil is dried out.
Wednesday, April 27, 2016
Possible Toe Wall Structures
During lab this week we brainstormed ideas for the toe wall, taking into account that the wall may need than just a single layer of bricks in terms of thickness and height.
Full-Scale Grid Materials
In our initial tests of the intra-soil grid we plan to use small, biodegradable planters and pots as materials. However, because of the obvious difference in size between our small scale-models and a full-scale implementation of this grid, we researched different materials that could be used on a full-size grid. We discovered that bamboo is both biodegradable and strong enough for our purposes. Bamboo plates (these for example: http://www.webstaurantstore.com/bambu-063200-9-disposable-square-bamboo-plate-25-pack/999063200.html), which would be structurally similar to the walls of a grid, are already on the market. The grid would be held in place by biodegradable stakes, such as the ones sold here: http://www.arbico-organics.com/product/biodegradable-ground-stakes/garden-tools-supplies.
Tuesday, April 26, 2016
Goals for Week 5 Lab
The goals for the lab this week is to start to design the intra soil grid system, work on the toe wall design with the materials we have and to plan out the rest of the week for meeting up.
Monday, April 25, 2016
Rain Simulation Improvements and First Simulation
This week we tried to focus on improving the rain simulation because it is one of the most important aspects of the project. It is the main factor we are considering in our study of soil erosion, therefore it is necessary for our tests to be completed. The team may have to make a trip for more materials, but this weekend we worked with the materials we have already purchased.
The first new material tested was an old t-shirt. First, we tried the t-shirt over the double layered screen but observed that the t-shirt absorbed the water instead of allowing the water to travel through it in a randomized pattern. Our next test was with one layer of the t-shirt, however this was still not an accurate simulation.
The next method we tried was the double layered screen by itself. We had tried this before but wanted to retest it because the materials were with us at the time. We discovered that if the screen was raised above the surface of the bin and the water was poured from a height above the screen, the water was more droplet like and random close to that of rain. We concluded that the height gave the water the droplet like effect while the screen having two layers made it more random. The following video is shown with the screen approximately 32 inches from the surface of the bucket and the water being poured from approximately 16 inches from the screen.
We are still open for testing new ways but after discovering this method was close to ideal we decided to simulate it on our test slope. The test slope has none of the proposed methods to slow soil erosion in place. Initially the length of the slope was 7.25 inches, the bottom leg was 6.50 inches, and the height was 4 inches. The average angle calculated was 30.46 degrees. After the rain simulation the slope length was 7.50 inches, the bottom leg was 6.75 inches and the height was 3.75 inches. These gave an average calculated angle of 28.30 degrees. These minor changes were not visible at first glance of the slope, but they coincide with the effects of soil erosion. The only visible change we saw initially was that the top edge of the slope appeared to be more round than edge-like from before. The following video gives a closer look than what we observed during testing. While watching if you focus on the edge of the slope the soil can be seen sliding down from the "rain."
This method of rain simulation is not finalized but the test was done to see what improvements can be made. Our next tasks are to make the rain fall consistent and determine the proper rate of rainfall.
The first new material tested was an old t-shirt. First, we tried the t-shirt over the double layered screen but observed that the t-shirt absorbed the water instead of allowing the water to travel through it in a randomized pattern. Our next test was with one layer of the t-shirt, however this was still not an accurate simulation.
The next method we tried was the double layered screen by itself. We had tried this before but wanted to retest it because the materials were with us at the time. We discovered that if the screen was raised above the surface of the bin and the water was poured from a height above the screen, the water was more droplet like and random close to that of rain. We concluded that the height gave the water the droplet like effect while the screen having two layers made it more random. The following video is shown with the screen approximately 32 inches from the surface of the bucket and the water being poured from approximately 16 inches from the screen.
We are still open for testing new ways but after discovering this method was close to ideal we decided to simulate it on our test slope. The test slope has none of the proposed methods to slow soil erosion in place. Initially the length of the slope was 7.25 inches, the bottom leg was 6.50 inches, and the height was 4 inches. The average angle calculated was 30.46 degrees. After the rain simulation the slope length was 7.50 inches, the bottom leg was 6.75 inches and the height was 3.75 inches. These gave an average calculated angle of 28.30 degrees. These minor changes were not visible at first glance of the slope, but they coincide with the effects of soil erosion. The only visible change we saw initially was that the top edge of the slope appeared to be more round than edge-like from before. The following video gives a closer look than what we observed during testing. While watching if you focus on the edge of the slope the soil can be seen sliding down from the "rain."
Friday, April 22, 2016
Building the Test Slope
The idea of the test slope is to find a "control value." The initial angle of the slope will be measured. Then, a load will be applied and the rain simulation will be run. After this, the new angle will be measured to see how much soil "erodes" with none of our proposed methods in place yet.
So far, two slopes have been built and tested with an applied load but not yet with the rain simulator, as we are in the process of finalizing this design. (It has been an ongoing task to optimize its performance).
Slope 1
The first slope created can be seen in the picture below.
After taking measurements of the slope length, the height of the soil, and the bottom leg an average angle of 42.89 degrees was found. After applying a load, none of the soil moved. We observed that we may have packed the slope more tightly than would naturally occur in nature. It is also important to note that in a natural environment a slope would be free on the edges.
Slope 2
We packed the soil in the second slope more loosely than that of the first.
We took the same measurements and redid our calculations. This time the slope angle was calculated to also be around 40 degrees, it was 42.40. This was not done intentionally. However after applying the same weight, noting happened to the slope.
Improvements to be Made
- Finalize the rain simulation technique to also use in testing.
- Line the two remaining sides of the plastic container to cause less sliding.
- Line the container with a material with greater friction.
- Test using different soil types - ones that may be dryer or pack loosely because these are the types of soil that erode more easily.
Tuesday, April 19, 2016
Rate of Rain Fall Test Proposition
We need to be able to simulate a set amount of rain fall for each test for consistency of data. A good range for our purposes should be between 1 and 2 inches/hour, but closer to 1 in/h would be better. 2 inch is the cusp of severe rain. To measure this I propose that we take a small beaker/test tube and place it in our rain test box. We run the rain simulation for 10 mins and measure the depth of the rain in the beaker. Then that value is multiplied by 6 (there are 6 intervals of 10 mins in 1 hour) which should give us the rainfall/hour. We should then run the test again to make sure that the data can be replicated.
Goal of Week 4 Lab
For today's lab, we decided to focus on the planning aspects of the project and make sure that everything can work together and we have all the pieces. It'll also allow us more time to test the project and each aspect rather than wait for one to finish testing to start the next piece.
Wednesday, April 13, 2016
New Sketches!
The above picture contains the original drawings of what we thought the rain maker system would look like as well as a brainstormed design for the toe wall. The toe wall design pictured above is a grid type design that gets its strength from its multiple square shapes and the screws that run
through the diagonal of each rectangle. Each node on the corners of the square doubles as a joint. As a result, the shape can be adjusted to fit curvature and lengths of hills. This also means that the wall can be added onto if necessary. Once this design this design is put into the ground, it cannot be adjusted.
The above sketch contains images of the rainmaker system as it was in the last lab. It is comprised of a 2 layer plastic screen made taught through a wood and metal square. 2 sides of the square are made from metal and the other 2 sides are made from wood.The metal sides are parallel to each other and double as sliders so that the square can lengthen in to a rectangle. This also allows us to put additional fabrics in between the two screens to create a more realistic rain effect. The fabrics we considered for this purpose are paper towel, weed block, and cheese cloth. we also considered leaving the screens bare but this requires lifting it above the bin at a certain height.
Lastly on this page, there is a model of our control test with limitations of this particular design.
This last page contains a few more designs that were thought of during the lab period. The first two are made of brick with the second requiring the cutting of said bricks to increase surface area and therefore increasing friction between the bricks. The third design consists of using a biodegradable material that will be layered together and weaved through several posts and placed into a thin trench around the hill.
Rain Simulation Testing
The design for the "Rain Simulation" altered again during our trip for materials at Home Depot. While there we found a screen that could be double layered and felt that it would work sufficiently as water "filter" to simulate rain instead of just pouring water. Here were a few of the methods we tested:
The Very Initial Design (Cheese Cloth as a Barrier)
Cheese cloth between the layers of screen. Note: The entire screen was not covered in this test, but was later on. |
As seen in the video, the cheese cloth did not give an even distribution of water as it fell. In other tests with cheese cloth it was too absorbent and did allow enough water to fall through at once.
Using Only the Screen
Screen purchased from Home Depot to use in rain simulation. |
In our opinion this method worked better than the cheese cloth. While the water was still not as distributed as we would have liked, it offered a better solution.
Using Weed Block
Originally we bought weed block to line the bins so the soil would not be directly on its plastic container. As the rain simulating testing continued we tried to see what other materials were available, and weed block was one. We decided to try it because we felt it was thick enough to keep the water from being a constant stream.
The weed block was by far the material that distributed the water the best. There were still some larger streams of water, but relative to the other materials they were much smaller. Weed block was also the only material that showed improvement by seeing "drops" of water come off of the screen. We thought we might be able to adjust this by pouring the water from a greater height.
The screen at a higher point above the container did have more "drop-like" water effects. As of right now, the weed block will be the material to use between the layer of screens.
Issues/Problems
- The screen tended to droop in the center which was also a cause of a water stream instead of droplets. This effect can be seen with all three test cases which is why it was not a fault with one in particular.
- The method of pouring water was also not the best it could be. We are looking into a material that could sit on the outer layer of the screen initially. This outer layer would pool the water until removed. When removed, the simulated rain can fall in all places at once rather than directly under where we are pouring.
- The height of the screen should stay consistent, therefore a structure may be built to keep the screen at a designated distance from the top of the container.
Tuesday, April 12, 2016
Soil Density/ Water Content Concern
The properties of soil can vary greatly depending on the water content, and if we don't account for that our data can be extremely erratic. I thought of a process to dry to soil post testing. We could lay it out on a large sheet of the weed block and apply pressure with some paper towels. Then we let it dry in the sun, and maybe finish it off with hair dryer. What do you guys think?
Monday, April 11, 2016
Weekend Update
On Sunday, April 10th, the group went down to Home Depot to get supplies for the project. With that, we can start testing the project and achieve results that will help us make the best project
Tuesday, April 5, 2016
Rain Simulation Design
Initial Rain Simulation Design:
The initial rain simulation design included wax paper and cheese cloth and a surface of wire screening over the control containment bin. After discussion, we realized cheese cloth was subject to puddling and the cells of the wire screening were far too large for rain simulation. With this design the "rainfall" would be more like a stream of water on the soil slope.
New Design 1:
The first new proposed idea we really liked for rain simulation was a 3-D printed grid model. The grid would have holes so small that once water was poured it would act more like rain drops. An issue we found with this was time. As it is currently Week 2 our control testing needs to be started and the drafting of this grid would need to be completed as well as the actual printing of it. We are still considering creating this grid for use later on in the term or to keep as a prototype. Check back frequently as the design will be posted once complete!
New Design 2:
We decided we may not need a 3-D printed grid, but rather could use any durable material to create the rain simulator. Once a material is chosen it can be sized to fit over our containment area and holes can be drilled into it. We have ruled out wood and corrugated plastic as these are water absorbent. Our other options include non corrugated plastic and metal. After looking at Home Depot online we found a few materials that may be ideal, but would like to visit the store to see them in person and gather other miscellaneous tools we may need throughout the term.
The initial rain simulation design included wax paper and cheese cloth and a surface of wire screening over the control containment bin. After discussion, we realized cheese cloth was subject to puddling and the cells of the wire screening were far too large for rain simulation. With this design the "rainfall" would be more like a stream of water on the soil slope.
New Design 1:
The first new proposed idea we really liked for rain simulation was a 3-D printed grid model. The grid would have holes so small that once water was poured it would act more like rain drops. An issue we found with this was time. As it is currently Week 2 our control testing needs to be started and the drafting of this grid would need to be completed as well as the actual printing of it. We are still considering creating this grid for use later on in the term or to keep as a prototype. Check back frequently as the design will be posted once complete!
New Design 2:
We decided we may not need a 3-D printed grid, but rather could use any durable material to create the rain simulator. Once a material is chosen it can be sized to fit over our containment area and holes can be drilled into it. We have ruled out wood and corrugated plastic as these are water absorbent. Our other options include non corrugated plastic and metal. After looking at Home Depot online we found a few materials that may be ideal, but would like to visit the store to see them in person and gather other miscellaneous tools we may need throughout the term.
More Background Information
After attending class today and hearing feedback from our advisor, the group thought it would be a good idea to provide a deeper understanding of how our project will be carried out. The "Week 1 Update - Planning" gives a brief outline of our plans but I would like to extend on that with the following.
The Three-Step Process
The toe wall is a necessary measure to stop soil from sliding any further down an eroded "dune." However, over time a toe wall would become subject to buckling due to the forces and pressure sliding soil puts on it. Our biodegradable intra-soil grid will be the next step to alleviate these pressures. It will provide a more stable structure for the soil. Both the intra-soil grid and the toe wall are still only temporary measures to soil erosion. They are to be put in place in an "Emergency Situation" to allow time for a permanent solution to be derived or implanted. The third step to our process - an erosion control blanket - may be the permanent solution of choice. The blanket will not only cover the surface of the area to keep the soil in place but contain plant seeds. Once these seeds are grown the extensive root network can provide a natural stabilization structure. This plant network is the main motivation behind using a biodegradable grid - it does not need to be removed and will eventually be replaced by the natural source.
The Control Environment and Its Purpose
We plan on creating a "control environment" which shows the sliding and erosion of soil prior to any of the measures discussed above. This environment will be a man-made slope of soil at a certain friction angle. Then a rain simulator will be used to "create" erosion within our model (see "Rain Simulation Design" for more information). After the simulation is run, we plan on measuring the change in angle.
Once the three step process is fabricated it will be tested by running close to the same simulation. It will differ by also adding a load to the top of the slope because only using rain simulation would not be a true indicator of our toe wall's success against sliding soil. The "success" of our project can then be determined if the change in slope angle during testing has decreased from that of the control environment.
Side Notes
The Three-Step Process
The toe wall is a necessary measure to stop soil from sliding any further down an eroded "dune." However, over time a toe wall would become subject to buckling due to the forces and pressure sliding soil puts on it. Our biodegradable intra-soil grid will be the next step to alleviate these pressures. It will provide a more stable structure for the soil. Both the intra-soil grid and the toe wall are still only temporary measures to soil erosion. They are to be put in place in an "Emergency Situation" to allow time for a permanent solution to be derived or implanted. The third step to our process - an erosion control blanket - may be the permanent solution of choice. The blanket will not only cover the surface of the area to keep the soil in place but contain plant seeds. Once these seeds are grown the extensive root network can provide a natural stabilization structure. This plant network is the main motivation behind using a biodegradable grid - it does not need to be removed and will eventually be replaced by the natural source.
The Control Environment and Its Purpose
We plan on creating a "control environment" which shows the sliding and erosion of soil prior to any of the measures discussed above. This environment will be a man-made slope of soil at a certain friction angle. Then a rain simulator will be used to "create" erosion within our model (see "Rain Simulation Design" for more information). After the simulation is run, we plan on measuring the change in angle.
Once the three step process is fabricated it will be tested by running close to the same simulation. It will differ by also adding a load to the top of the slope because only using rain simulation would not be a true indicator of our toe wall's success against sliding soil. The "success" of our project can then be determined if the change in slope angle during testing has decreased from that of the control environment.
Side Notes
- Soil from various places will be used for testing (Delaware County, The Pine Barrens of New Jersey).
- Durable and cost efficient materials will be researched. The proper material may also depend on the origin of the soil.
Monday, April 4, 2016
Week 1 Update - Planning
Week 1 of our Emergency Soil Stabilizer project consisted of forming a solution for the issue of rapid soil erosion. The initial design is composed of an immediate toe wall followed by an underground grid and a surface blanket. The toe wall and underground grid are temporary measures to provide structural support before the surface blanket is applied. The underground grid will be biodegradable to eliminate the need for removal. The surface blanket will contain plant seeds to provide a more permanent solution, as these plants will grow roots that stabilize the soil.
This design is projected to be completed in a ten week period. Below is an outlined schedule on a week to week basis. This blog will be updated weekly with our progress.
This design is projected to be completed in a ten week period. Below is an outlined schedule on a week to week basis. This blog will be updated weekly with our progress.
Subscribe to:
Posts (Atom)